September 1, 2009

CAMP UPDATE #11

August 28, 2009


More progress this week. The fireplace is finished on the outside, all the windows and siding have been installed and the deck is almost complete as of September 1, 09. The crew was starting the deck steps when we left today (The pictures for this posting were taken on August 28 and do not show the deck railing in place.)

In addition, the basement stairs are being installed, the tub and toilet have been delivered, the fridge, dishwasher and stove are ordered and will be coming soon, the air exchange has been installed and the electrical inspection is scheduled for tomorrow. Once the inspection is done they can start the insulation and gyprock. Jamie Keen is coming this weekend to start the kitchen.

We are doing are best to retain our sanity during this whirlwind of activity.