CAMP UPDATE #9

When I left Digby on August 6th the guys were putting on the blueskin and styrofoam insulation over the housewrap. The soffits are just about finished and the electriction has been by to hook in the shed, prepare the main 200 amp feed for the NS Power Corp to hook into and install some outside lighting fixtures. The phone line now goes into the shed via conduit.

The siding arrived a couple of days ago and the doors/windows should be on site in a day or two. I worked on getting the pumpup tiolet installed and was able to get most of the work done. A few more fittings are required to complete the job.